January 2007 Progress report
article by: John McMillan
We've spent a good deal of time this quarter re-visiting some
jobs which, for various reasons, were not quite finished
originally.
An example of this is the pipe work between the frames.
This work was underway when the boiler was out of the frames, and
access was easy. The day the boiler returned to Toddington, it had
to go straight onto the loco chassis, and this brought the pipe
work job to a halt. With the boiler raised at present for
assembly of the cladding, we've taken advantage of the improved
access to get between the frames and finish off some of the pipe
work jobs. A number of pipe clamps and protective sleeves
have been made in the machine shop, along with pipe couplings, as
none of these parts are commercially available.
After the loco had been moved around the yard during various
shunts, we noticed that the drain cock pipes from the centre
cylinder had been knocked out of position. Closer examination
revealed that the front bogie chassis had come into contact with
the pipes due to some of the tight curves in the yard. A check with
the drawings revealed that the pipes had been fitted correctly to
the drawing, but it seems that "Merchant Navies" weren't intended
to negotiate such small radius sections of track. The mounting
brackets for the pipes have been re-positioned, and the pipe runs
adjusted to give the front bogie a little more room to swing.
We hope there's enough room now!
Still up at the front end of the loco, work continues on fitting
the lagging and cladding to the cylinders. About half of the
lagging pads have been made and fitted to the right hand cylinder,
and the long job of making good all the mating surfaces continues,
with the aim of achieving perfectly flat surfaces forming
steam-tight joints.
The running boards have been on and off the loco many times over
the years, but some have been re-fitted so that wiring conduit
clamps could be accurately positioned and welded in place.
Also, the sand-pipe deflector plates have been made. These
fit around the base of the sand filler pipes to prevent spilt sand
dropping into vulnerable areas as the sand boxes are being
filled. In addition, they provide bracing between the filler
pipes and running boards, which makes for greater sturdiness all
round. As the filler pipes had to come off to fit these
plates, we took the opportunity to correct the alignment of one of
the filler pipes.
The last two sheets of boiler cladding have been fabricated and,
after careful measurements, were fitted in place; they look very
good indeed. Numerous pockets for boiler fittings, mud hole
doors, and washout plugs have been riveted onto various sections of
cladding using copper rivets, and the boiler bands have all been
made together with their tensioning clamps. There is just one more
awkward cover for a pipe on the driver's side of the firebox to
make, and the nameplate mountings need to be fitted, but otherwise
the boiler cladding is complete. This is a substantial step
forward in the restoration, though it has all got to come off again
for the steam test and fitting of the lagging. Then there's the
matter of painting and lining out, jobs for the future!
On the underside of the boiler barrel, towards the rear, there
is a large inspection plate called the Belly Plate. During
overhauls, the plate can be removed and the inside of the bottom of
the boiler barrel cleaned and examined. The original plate
was removed and stored many years ago but when we came to it again,
its condition was such that we decided to have a new plate
made. The studs that hold it in position were still in the
boiler and it took considerable skill and patience to remove each
stud without shearing any off. New studs have now been
fitted, and we've learned to be cautious with our boiler, as the
Belly Plate mounting tried to catch us out. Careful
examination of the plate revealed that when it was made the
operator didn't get the distances between the studs quite right,
resulting in some being slightly closer together than others.
We have had to replicate this error accurately so that our new
plate will fit the boiler.
A start has been made on machining the tender hand-brake
mechanism. This section fits within the hand-brake support
bracket and has a coarse square section thread through which the
hand-brake shaft moves when the fireman applies the brakes.
The external shape of the part has been roughly machined, but we've
yet to start on the very tricky task of cutting the thread.
There's a pair of small but intricate pipe couplings between the
loco and tender for one of the vacuum pipes. We had borrowed the
fittings from 35005 so that we could take measurements and make a
drawing, but we had an anxious member of the loco department asking
for it back, as 35005 was scheduled to haul trains later that
day!
A candidate casting for the tender brake-block holders was
obtained and machined to match the brake-blocks we intend using,
and the brake hanger arms. One complete assembly was then fitted up
on the tender, and the brake-block lined up perfectly with the
wheel. The completed holder and a drawing have been sent to a
pattern maker so that we can have a quantity made.
The dished end ends for the vacuum reservoir tanks have had
their new pipe fittings welded in place and the ends are now ready
to be welded into the cylindrical section of the tanks, once we can
find someone to make the cylinders. We are impressed with the
new smoke box made for "Owsden Hall", and will be making enquiries
concerning where it was made, and can they make smaller cylinders,
please? Indeed we would be pleased to hear from anyone who may be
able to direct us to a firm who can make small, pressurised
cylinders. We can be contacted via the website.