Carriage & Wagon Report March 2011
article by: Richard Johnson
A lot has happened at the Railway since my last report. In
October I reported that we had just started on a plan to refurbish
several of the chocolate & cream set of coaches for 2011. This
set had been in almost continuous daily use for several years, and
was looking the worse for wear.
The plan was to take as many of the coaches into our workshop as
possible throughout the winter one after the other, and smarten
them up. We started with the TSO (Tourist second Open) 4763 because
whilst it was in basically good condition, it was painted carmine
& cream. We brought it into our workshop in October and work
began immediately on a fresh external paint job.
The opportunity was taken to give the interior a heavy clean and
generally freshen it up, as the coach had been in use for three
years since first being refurbished. Repairs were undertaken to the
seating, the lino flooring, and the toilets were given a thorough
clean. 4763 went back into use at the beginning of December
in time for the Santa trains, fully painted lined and
varnished.
We then had to complete the refurbishment of the FO (Open First)
3045 from the Elegant Excursions set. This coach had been worked on
for virtually the whole of 2010, after it was taken out of use at
the beginning of the year, for what was optimistically thought to
be a 'repaint'. In the event it had a huge amount of work done to
it; not least 6 brand new external doors were manufactured by the
department, and it was completely repanelled internally. We
completed it one day before it went back into use in the dining
train in mid December.
It was replaced by the FK (Corridor First) 13329, which again
was carmine & cream so needed a repaint. An initial inspection
showed that there were a number of areas where the bodywork was in
need of repair, and quite rightly the decision was taken that it
was better to do the repairs properly, rather than just a quick
fix. So, two external windows with their frames were removed so
that rotten sections of bodyside could be cut out, which in turn
revealed that leaking had rotted the internal woodwork which had to
be replaced.
The vestibule floor at the south end had always been a bit
'bouncy', and had been patched up a couple of years ago. The
opportunity was taken to have a good look. It revealed - inevitably
- that not only was the flooring largely rotten, but so was much of
the steelwork underneath. It was all caused by a leak from an
adjacent toilet cistern. It was all replaced, and a flooring
contractor fitted brand new marmoleum flooring. Following a full
repaint, 13329 was lined out, numbered and varnished, and went back
into the operational rake in mid February.
We extracted the other TSO 4772 from the chocolate & cream
rake at the same time, and that came into our workshop to replace
the FK. We knew that there would be some bodywork repairs, but have
found more than we expected. This coach had been in continuous use
since 2004, when it was first refurbished and put into use.
The pictures show the area of one of the toilets. The floor was
rotten, and it had been locked out of use. Once the floor was taken
up, it revealed rotten steel bracing, and as more investigations
were made, rotten bodyside members and panelling. This will all
need to be replaced before the wooden floor can be replaced. At the
other end, we found the vestibule floor to be rotten due to a
leaking radiator. The flooring has all been removed and is being
replaced.
As before this coach will have a thorough job done on it, and it
will be repainted in chocolate & cream, lined and varnished.
The plan is to try and get it ready for mid April when services
from Winchcombe start. It will be a close run thing. Once again, we
have taken the decision to do the job thoroughly and properly,
rather than give it just a rushed 'quick fix'.
Work has been progressing on the RBr 1672. It went into our Barn
in November and has been jacked up ever since, so that the steam
heating pipework underneath could be replaced. Whilst not quite
finished yet, it is nearly so. Some secondary connections from the
main pipe to the radiators remain to be done. We intend to try and
finish this coach by about the middle of 2011, so that it can go
into use and replace 1675 which needs a rest.
Our plans for the new season have been thrown into a bit of
turmoil by the collapse of the embankment at Chicken Curve. What it
means to us is that the new timetable provides for one train a day
from Winchcombe to Cheltenham; five days per week. The plan is to
use the chocolate & cream set every running day, so we need to
make doubly sure all is Ok, and work out how we can deal with
routine maintenance and servicing. Our maroon set which is also at
Winchcombe, will be kept as a strategic reserve, and will be used
for firing and driving courses.
Returning to our workshop, we have been working on a standard
GWR box van No. 124589. It was built at Swindon in 1936. The van
was a wreck when work started. Much of the bodyside planking was
either rotten, or was missing. Also, there were large sections of
the wooden roof which had been missing for some time, leaving much
of the flooring rotten.
All defective woodwork has now been replaced, and the van is
being painted GWR grey, with a light grey canvas roof. Underneath,
the brake system has been stripped, overhauled and has been
rebuilt. When it is completed, not only will it be another
operational GWR van, it will also provide more dry secure
storage.
That really just leaves the BG (Gangwayed Brake) 92350. This
vehicle was acquired some months ago by the Permanent way
department, for use as their new mess coach. The initial problem we
had was the state of the bodyside doors (of which there are 18).
Many have had to be stripped, and repaired, with two being
completely replaced. One section internally will be converted
into a kitchen. It is currently being built as such and fitted
out.
The BG will be turned out in all over maroon, as it was when
first built in the 1950's. There is still a lot to do to it before
it can be used. It will have to shunted onto our jacks, and be
lifted so that we can sort it out underneath. We need to reinstate
the vacuum through pipe initially. In due course, the full braking
system will be rebuilt.
As you will have read elsewhere the railway has suffered the
minor inconvenience of another embankment slip; this time between
Toddington and Winchcombe. This means that we shall be playing host
to several steam locomotives and their crews at Winchcombe this
year. The sidings were congested at Winchcombe last year, so this
coming year will be 'interesting'.
The first major indication of the imminent arrival of the loco
department is that a pit needs to be built to service the locos,
whilst at Winchcombe. Work is going to start on 6th
April, and it will take 6 weeks.
This means that for the whole of that period, shunting will not
be possible, so we have had to make urgent plans to make sure that
the stock is where we need it to be before the workshop is
isolated. All being well, 4772 will be ready to emerge chrysalis
like from our workshop, just as the concrete has set and the pit
rails are laid to connect us back with the outside world. That, in
any event is the master plan.
Finally, as our contribution to the current difficult financial
situation the railway faces, the Carriage & Wagon department
has decided to organise two public Open weekends on 25th
/ 26th June and 2nd / 3rd July.
There will be demonstrations of the various different types of work
we do, and sales stands with a wide variety of different railway
items on sale. We hope both to substantially increase passenger
numbers, and see a good many visitors over the four days of the
event.
Please put these dates in your diary, and come along and see us
with friends and family. There will be no charge to come in to our
event, but you may well want to make a small donation to our funds
as you leave.