Carriage & Wagon Report October 2004
article by: Richard Johnson
At the time of the last report, we had just finished the Open
First 3045 'Marguerite' and put it back into service. Immediately
afterwards we brought the RBr (Restaurant Buffet) 1675 back into
the shed. This turned out to be a very good move, because it
enabled us to concentrate on finishing off all those jobs which we
all tend to leave to someone else.
All the panelling in the corridor was completed and has been
painted in executive grey. We decided to do this, because much of
it was originally distorted and rotten and has had to be replaced.
It was not feasible to replace it with formica of the original
pattern, so repainting was the best option. The flooring in front
of the buffet counter has been re-laid, and a whole host of minor
but important items inside have been attended to. Only minor
plumbing work is now required underneath, and it is finished,
(hopefully!). The plan is to run it in on the services after the
Santa trains in late December for a 'shake down', so that will be
your first opportunity to travel in it.
Presently occupying all our time in the shed is the TSO (Tourist
Second Open) 4772 which we acquired from Paignton earlier this
year. It is now largely complete underneath, having been lifted on
the carriage jacks whilst the RBr was inside. Work continues to
smarten up the inside, and externally it is being transformed into
chocolate & cream. Five of the exterior doors now work
perfectly. When we obtained the coach, all doors had swollen up (as
they do) and were stuck solid. Two were so rotten that they had to
be taken off and thrown into a skip. The coach arrived without any
internal tables, but we have acquired a full set of 16 and they
will be fitted before it leaves us to go into service The plan is
to have the coach available for the first of the Santa trains in
early December. It is always good to know that there is a plan!
With the entry into service of the RBr and the TSO, it will
release the RMB (Miniature Buffet) 1811, and the SK (Corridor
Second) 25451 from the Chocolate & Cream set. 25451 is in need
of a refurb, having run for 10 years since we last did it. It will
re-emerge in Carmine & Cream and be the fifth vehicle in that
rake. 1811 will be refurbished later, and held as a spare
buffet.
The Southern Railway brake van 55126 (see picture) has been
completed mechanically and externally, and operated in the freight
train on the Diesel Gala on the 16th & 17th of October. In
addition to a thorough repaint, several of the windows were
replaced, new doors to the guards cabin were manufactured and
fitted and new flooring was installed throughout. It needs to come
back to us to have some internal finishing, but it was too good an
opportunity to miss, to see it in operation.
Work is continuing on the 1932 Great Western Mink G 112850. This
is a 20 ton 4 wheeled goods van, which is being put back into its
original GWR colours. I read somewhere that these were the longest
4 wheeled vans ever built, and it is quite possible. Longer
vehicles tend to have bogies, to enable them to negotiate curves as
well as to distribute the weight better. The braking system
underneath this van has now been completed. Some missing rodding
has been replaced, and a refurbished vacuum brake cylinder has been
fitted. There is still an amount of body woodwork to be completed,
and a new canvas roof covering has to be fitted. Quite apart from
looking very attractive, when completed it will both become a very
useful stores vehicle, and will be available to be operated in
demonstration goods trains.
New roller shutter doors have now been fitted at both ends of
the shed, and the old rickety steel framed clad doors were taken
down and cut up. Had we left it any longer, it is likely that they
would have fallen down of their own accord. With the advent of
colder weather we have tried out our new space heater for the first
time. It is much more efficient than the old one it replaced, and
should keep everyone warm throughout the winter, so no excuses.